recently, inner mongolia huaheng energy ptmeg, pbat new material industry chain integration project supporting construction of 240,000 tons/year calcium carbide project and wuhai guangjin new material co., ltd. bdo-pbat integrated project supporting construction the 360,000 tons/year calcium carbide project is approved for filing.
(1) huaheng energy ptmeg, pbat new material industry chain integration project supporting construction of 240,000 tons/year calcium carbide project
construction site: wuhai city—hainan district—low carbon economy industrial park, hainan district, wuhai city, inner mongolia
total investment: 600 million yuan, including 600 million yuan of self-owned funds, 0 yuan for bank loans, and 0 yuan for others
planned construction start and end years: 2023/08 to 2025/08
construction scale and content: construction of 240,000 tons/year calcium carbide project. it covers an area of 540 mu (360180 square meters). construction of 400,000 tons/year lime plant, 240,000 tons/year calcium carbide plant and supporting public and auxiliary facilities. among them, the lime plant adopts two 800t/d double-chamber vertical kilns, and the calcium carbide plant adopts four 48000kva sealed calcium carbide furnaces.
(2) guangjin new materials co., ltd. bdo-pbat integrated project supporting construction of 360,000 tons/year calcium carbide project
construction site: wuhai city - hainan district - low carbon industrial park in hainan district, wuhai city, inner mongolia.
total investment: 947.0292 million yuan, including 947.0292 million yuan of self-owned funds, 0 yuan for bank loans, and 0 yuan for others
planned construction start and end years: 2023/09 to 2024/12
construction scale and content: the project plans to build a bdo-pbat integrated project of wuhai guangjin new materials co., ltd. in the low-carbon industrial park of hainan district, wuhai city, inner mongolia to build a 360,000-ton/year calcium carbide project. it covers an area of 2,796.70 mu (about 1,865,400 square meters). construct 600,000 tons/year lime plant, 360,000 tons/year calcium carbide plant and supporting public and auxiliary facilities. among them, the lime plant adopts 5 sets of 800t/d double-chamber vertical kilns, and the calcium carbide plant adopts 6 sets of 48000kva sealed calcium carbide furnaces (5 open and 1 standby).